61: Establish Architecture Review Process
Specification Version: 2.0.0
Status: Accepted
Slug: 61-architecture-review
Implementation Types:
- None
Descriptive Statement
Establish intake/review process for new and existing architectures.
Supplemental Guidance
These are scored as a bucket because you can do them in any order. Most practices name an approver long before anyone writes down which designs are supposed to come to review at all.
Item 1 should typically be done first, though nothing stops a practice documenting a trade-off model or naming an approver before it settles which designs have to come to review at all. The capability describes the immature state as decisions made case by case, which is what a review with no defined trigger produces. The threshold is yours to set, but it has to be written down, because an unwritten threshold means the trigger is whoever remembered to ask.
Without the stated signals in item 2, a review works through whatever arrived first, which is how a small change jumps a large one.
The five dimensions in item 3 are from the Framework’s list. A practice weighing only cost is doing a cost review, not a placement review, and will keep approving designs that are cheap and fragile.
Action 62 scores the modernization review, including its cadence and exception criteria, so cadence is not scored here. Action 63 scores estimating the trade-offs for a given case. This action scores the model the review applies and the gate it sits behind. Action 64 tracks actual cost against estimated savings per iteration, so item 5 is narrower: it asks only whether the review’s own model gets corrected when a build diverges from what was approved.
Scoring Guide
Weight: 1.0
Formula
Measured over: the review process itself for items 1 to 3, and every review conducted during the period for items 4 and 5. Reviews are few enough to enumerate, so those two are assessed against each review rather than as a coverage rate.
- Intake trigger defined (which designs enter review: new builds, material changes, and spend above a stated threshold)
- Triage signals stated (candidates are prioritized using spend, usage, value, and adoption signals rather than order of arrival)
- Trade-off model documented (the review weighs cost, value, sovereignty, resilience, and sustainability)
- Approver named (the role that approves a placement decision and accepts its trade-offs is recorded for each review)
- Model updated from outcomes (the review records whether what was built matched what was approved, and the trade-off model changes when it did not)
10*Ceil(x/5)
Scoring Details
Score Type: bucket
| Score | Condition |
|---|---|
| 0 | No items completed |
| 2 | 1 item completed |
| 4 | 2 items completed |
| 6 | 3 items completed |
| 8 | 4 items completed |
| 10 | 5 items completed |
References
- Finops Framework - Architecting & Workload Placement Capability: Every item is taken from the capability’s own language. Its Run tier expects formalized triage and review processes that prioritize candidates using spend, usage, value, and adoption signals, and its Walk tier expects a documented model weighing cost, value, sovereignty, resilience, and sustainability.
- Nist Csf 2.0 - Id.ra-07: “Changes and exceptions are managed, assessed for risk impact, recorded, and tracked.” An intake review is the point where a design change is assessed before it is built rather than after the invoice arrives.
- Finops++ Score Type - Bucket: an evolution of binary, with more steps to take toward maturity.